Irrigation Project Contract Extension Act of 1996 - Directs the Secretary of the Interior to extend for an additional four years each of eight specified water service contracts entered into under the Reclamation Project Act of 1939 and the Flood Control Act of 1944 as irrigation projects in Kansas and Nebraska as part of the Missouri River Basin Project.
Irrigation Project Contract Extension Act of 1996
This bill became law
What it doesSummary passed senate amended (Sep 28, 1996)
Irrigation Project Contract Extension Act of 1996 - Directs the Secretary of the Interior to extend for an additional four years each of eight specified water service contracts entered into under the Reclamation Project Act of 1939 and the Flood Control Act of 1944 as irrigation projects in Kansas and Nebraska as part of the Missouri River Basin Project.
What just happenedOct 19, 1996
Became Public Law No: 104-326.
Who’s behind it
- Enrolled BillOct 4, 1996
- Engrossed in SenateSep 28, 1996
- Reported to SenateSep 16, 1996
- Introduced in SenateMar 28, 1996
- Public LawOct 20, 1996
- Oct 19, 1996PresidentE40000
Became Public Law No: 104-326.
- Oct 19, 1996BecameLaw36000
Became Public Law No: 104-326.
- Oct 19, 1996PresidentE30000
Signed by President.
- Oct 19, 1996BecameLaw36000
Signed by President.
- Oct 9, 1996FloorE20000
Presented to President.
- Oct 9, 1996President28000
Presented to President.
- Oct 4, 1996FloorH38310
Motion to reconsider laid on the table Agreed to without objection.
- Oct 4, 1996FloorH37100
On passage Passed without objection.
- Oct 4, 1996Floor8000
Passed/agreed to in House: On passage Passed without objection.
- Oct 4, 1996FloorH30200
Mr. Solomon asked unanimous consent to take from the Speaker's table and consider.
- Oct 4, 1996FloorH30000
Considered by unanimous consent. (consideration: CR H12292)
- Sep 30, 1996Floor
By Senator Murkowski from Committee on Energy and Natural Resources filed written report. Report No. 104-380.
Energy and Natural Resources Committee - Sep 30, 1996Committee14900
By Senator Murkowski from Committee on Energy and Natural Resources filed written report. Report No. 104-380.
Energy and Natural Resources Committee - Sep 28, 1996FloorH15000
Held at the desk.
- Sep 28, 1996Floor
Message on Senate action sent to the House.
- Sep 28, 1996FloorH14000
Received in the House.
- Sep 28, 1996Floor
Passed Senate with amendments by Unanimous Consent. (consideration: CR S11667-11668)
- Sep 28, 1996Floor17000
Passed/agreed to in Senate: Passed Senate with amendments by Unanimous Consent.(consideration: CR S11667-11668)
- Sep 16, 1996Calendars
Placed on Senate Legislative Calendar under General Orders. Calendar No. 604.
- Sep 16, 1996Committee
Committee on Energy and Natural Resources. Reported to Senate by Senator Murkowski with amendments. Without written report.
Energy and Natural Resources Committee - Sep 16, 1996Committee14000
Committee on Energy and Natural Resources. Reported to Senate by Senator Murkowski with amendments. Without written report.
Energy and Natural Resources Committee - Sep 12, 1996Committee
Committee on Energy and Natural Resources. Ordered to be reported with amendments favorably.
Energy and Natural Resources Committee - Sep 5, 1996Committee
Subcommittee on Forests and Public Lands. Hearings held. Hearings printed: S.Hrg. 104-774.
Public Lands, Forests, and Mining Subcommittee - May 1, 1996Committee
Committee on Energy and Natural Resources requested executive comment from Department of the Interior, and Office of Management and Budget.
Energy and Natural Resources Committee - Mar 29, 1996Committee
Referred to Subcommittee on Forests and Public Lands.
Public Lands, Forests, and Mining Subcommittee - Mar 28, 1996IntroReferral
Read twice and referred to the Committee on Energy and Natural Resources.
Energy and Natural Resources Committee - Mar 28, 1996IntroReferralB00100
Sponsor introductory remarks on measure. (CR S3157)
- Mar 28, 1996IntroReferral10000
Introduced in Senate
Irrigation Project Contract Extension Act of 1996 - Directs the Secretary of the Interior to extend for an additional four years each of ten specified construction repayment and water service contracts entered into under the Reclamation Project Act of 1939 and the Flood Control Act of 1944 as irrigation projects in Kansas and Nebraska as part of the Missouri River Basin Project.